Walls and Roof

The building envelope involved constructing 2x6 walls with polyiso nailbase over existing slab and Zola windows. Outer finish is fire retardant stucco.

Subslab assembly

Over existing garage slab was a vapor barrier followed by 12" EPS then conventional floor framing bearing on existing walls, R 52. Existing sloped crawlspaces 3" ccsf (R20) over vapor barrier on ground. There was an existing basement slab that remained uninsulated of 723 sf.

Subslab R-value 52.0
Foundation wall assembly

basement walls 4" polyiso against concrete with dense pack cellulose in 2x4 interior stud cavity

Above grade wall assembly

Remodel/new construction 4" polyiso nailbase over 2x6 OVE 24" O.C. framing with netted and blown cellulose

Above grade wall R-value 35.0
Cathedral ceiling assembly

18" netted and blown dense pack cellulose in trusses

Cathedral ceiling R-value 64.0
Roof Assembly

Roof made with composite asphalt shingles from Certainteed rated as Landmark impact resistant: UL2218 Class 4 rating

Windows and Doors

Window Assembly:

Zola Thermoclad

Door Assembly:

Zola Thermoclad

Average window U-factor 0.15
Solar Heat Gain Coefficient 0.50
Door U-Factor 0.15
Door Area 124 sq ft

Mechanical Systems

Space cooling - Manufacturer & Model ClimateMaster Q45 Trilogy ground source heat pump
Space heating - Manufacturer & Model ClimateMaster Q45 Trilogy ground source heat pump
Domestic hot water - Manufacturer & Model ClimateMaster Q45 Trilogy ground source heat pump w/integrated GDHM 80-gal tank with 10 kW electric backup
Domestic hot water - capacity 80 gal
Ventilation - Manufacturer & Model ERV Ultimate Air 200dx
Lighting Manufacturer and Model 95% LED
Lighting Efficiency
Mechanical Equipment Installation Details and Comments

Forced air hard ducted system for heating and cooling; separate ERV duct system with flex duct at termination for noise control. ERV jumper ducts at bedrooms.

Envelope

Air Changes per hour, ACH50 0.49 ACH50
Air Changes per hour, CFM50 399.00